Preliminary Study on Valuation Methods for Geothermal Power Plant Asset Transfers in Indonesia
Keywords:
valuation, assets, GPP, risk, useful life, asset transfer, BOOTAbstract
One of the clauses in the Power Purchase Agreement between PLN and IPP, especially in the BOOT cooperation scheme, is the transfer of assets. However, there are no further rules regarding the mechanism of asset transfer and asset valuation, particularly for GPPs, which have high-cost structures but also high uncertainty, especially in the initial exploration phase. The absence of standard rules may lead to significant differences in the value of assets with similar technical characteristics. This paper will conduct an initial study on an appropriate asset valuation approach for GPPs, taking into account various factors. Based on the analysis, geothermal asset valuation should use a more integrated approach tailored to the project stage and consider many factors, including remaining operating life, both technical and economic, the level of risk inherent in each project stage, and the perception of fair value for both parties to the transaction.
Downloads
References
Ministry of Energy and Mineral Resource Republic of Indonesia, Handbook of Energy & Economic Statistics of Indonesia 2023, Ministry of Energy and Mineral Resource, 2023.
PT PLN (Persero), Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) 2025–2034, PT PLN (Persero), 2024.
Kementerian Energi dan Sumber Daya Mineral Republik Indonesia, Peraturan Menteri ESDM Nomor 10 Tahun 2017 tentang Pokok-Pokok dalam Perjanjian Jual Beli Tenaga Listrik, Jakarta, 2017.
Gatti, S., Project Finance in Theory and Practice: Designing, Structuring, and Financing Private and Public Projects, ed. 1, Academic Press (Elsevier Inc.), 2008.
Ralahallo, F.N., Jaya, F.H. & Tukimun, Manajemen Proyek, ed. 1, Sulur Pustaka, 2024. (Book)
Kementerian Keuangan Republik Indonesia, Peraturan Menteri Keuangan Nomor 173/PMK.06/2020 tentang Penilaian oleh Penilai Pemerintah di Lingkungan Direktorat Jenderal Kekayaan Negara, Jakarta, 2020.
Saptadji, N.M., Ashat, M.A. & Maulana, D.T., Teknik Produksi Geotermal, ed. 1, ITB Press, 2023.
ESMAP, Geothermal Handbook: Planning and Financing Power Generation, Technical Report 002/12, Energy Sector Management Assistance Program, The World Bank, 2012. (Book)
Kassem, M.A., Moscariello, A. & Hollmuller, P., Navigating risk in geothermal energy projects: A systematic literature review, Energy Reports, vol. 13, pp. 696–712, 2025. https://doi.org/10.1016/j.egyr.2024.12.052. (Journal)
Steiger, F., The Validity of Company Valuation Using Discounted Cash Flow Methods, Seminar Paper, European Business School, Fall 2008. (Paper)
Jaja, I., All About Corporate Valuation, ed. 1, PT Elex Media Komputindo, Kompas Gramedia, 2017. (Book)
Dewi, M.P., Setiawan, A.D., Latief, Y. & Purwanto, W.W., Investment decisions under uncertainties in geothermal power generation, AIMS Energy, 10(4), pp. 844–857, Jul. 2022.
Bilqist, R.A., Dachyar, M. & Farizal, Project valuation in the geothermal power plant project: A comparison of Expected Net Present Value and static Net Present Value approaches, SSRN, https://ssrn.com/abstract=3248120, (16 Juni 2025). (URL Link)
Bilqist, R.A., Dachyar, M. & Farizal, The Valuation of Geothermal Power Projects in Indonesia Using Real Options Valuation, MATEC Web of Conferences 248, pp. 1–6, 2018. (Conference Proceedings)
Martono, A.S., Dasar-Dasar Penilaian Aset dan Properti, ed. 1, LP3E FE-UI, 2002. (Book)
Royal Institution of Chartered Surveyors (RICS), The Valuation of Assets in the Commercial Renewable Energy Sector, ed. 1, RICS, 2018. (Book)