Technical Feasibility Analysis of the 500 kV Extra High Voltage Overhead Transmission System Project in Sumatra

Authors

  • Trisno Dharma Putra PT PLN (Persero)
  • Kevin Marojahan Banjar-Nahor School of Electrical Engineering and Informatics, Institut Teknologi Bandung
  • Nanang Hariyanto School of Electrical Engineering and Informatics, Institut Teknologi Bandung
  • Nanang Hariyanto School of Electrical Engineering and Informatics, Institut Teknologi Bandung

Keywords:

Index Terms—500 kV Transmission Line, Feasibility Study, Electricity Market Optimization

Abstract

The 500 kV Extra High Voltage Transmission Line project in Sumatra is a critical infrastructure initiative designedto improve the efficiency and reliability of power transmission across the island. This study evaluates the technical feasibility of the project by analyzing key aspects such as operational efficiency, structural integrity, and environmental impact. The project aims to address growing energy demands in Sumatra while resolving bottlenecks in the existing 275 kV transmission system. It also facilitates the integration of renewable energy sources, such as geothermal and hydroelectric power, into the grid, contributing to a reduced reliance on fossil fuels and supporting Indonesia’s transition toward sustainable energy. The findings suggest that the project will significantly enhance the stability of the Sumatra power grid, optimize energy distribution, and promote environmental sustainability. Overall, the project is deemed feasible and essential for securing the region’s long-term energy needs.

Downloads

Download data is not yet available.

References

D. F. Hakam, A. Luqman, and T. Fahrudin. Sustainable energy production in sumatra power system. 2012.

Ashraf Balametov, Elman Halilov, and Tarana Isayeva. Extra high voltage transmission line operation simulation using the actualcoronaloss characteristics. Turkish Journal of Electrical Engineering and Computer Sciences, 26(1):479–488, 2018.

Min Jiang Chen, Bei Wu, Sheng Hu Li, and Yue Qing Chen. Sensitivity model to power flow control capability using controllable series

compensators. Advanced Materials Research, 1070:929–937, 2015.

E Sheeba Percis, L Ramesh, Shwetha Kaushik, et al. Performance analysis of off shore wind energy systems using hvdc transmission.

Bhaskar Mitra, Badrul Chowdhury, and Madhav Manjrekar. Hvdc transmission for access to off-shore renewable energy: a review of

technology and fault detection techniques. IET Renewable Power Generation, 12(13):1563–1571, 2018.

Daniel Ludois and Giri Venkataramanan. An examination of ac/hvdc power circuits for interconnecting bulk wind generation with the electric grid. Energies, 3(6):1263–1289, 2010.

Matheus Sene Paulo, Andrei de Oliveira Almeida, Pedro Machado de Almeida, and Pedro Gomes Barbosa. Control of an offshore wind

farm considering grid-connected and stand-alone operation of a highvoltage direct current transmission system based on multilevel modular converters. Energies, 16(16):5891, 2023.

Yi Luo, Shiyi Mao, Ju Tang, Zijun Pan, and Cheng Pan. Shape optimisation of basin insulator for dc gas insulated switchgear/gas

insulated transmission lines based on artificial bee colony algorithm. High Voltage, 9(2):275–286, 2024.

Shamsul Fahmi Mohd Nor, Mohd Zainal Abidin Kadir, Azrul Mohd Ariffin, Miszaina Osman, M. S. Abd Rahman, and Noorlina Mohd

Zainuddin. Systematic approaches and analyses on voltage uprating of 132 kv transmission lines: A case study in malaysia. Applied Sciences, 2021.

Shamsul Fahmi Mohd Nor, Mohd Zainal Abidin Kadir, Azrul Mohd Ariffin, Miszaina Osman, M. S. Abd Rahman, and Noorlina Mohd

Zainuddin. Issues and challenges in voltage uprating for sustainable power operation: A case study of a 132 kv transmission line system in malaysia. Sustainability, 2021.

Ikhlas Kitta. Tropical climate effects on corona power losses on 275 kv transmission lines in the south sulawesi system. Przeglad

Elektrotechniczny, 2019.

Downloads

Published

2025-01-21

How to Cite

Putra, T. D., Banjar-Nahor, K. M., Hariyanto, N., & Hariyanto, N. (2025). Technical Feasibility Analysis of the 500 kV Extra High Voltage Overhead Transmission System Project in Sumatra. ITB Graduate School Conference, 4(1). Retrieved from https://gcs.itb.ac.id/proceeding-igsc/index.php/igsc/article/view/353

Issue

Section

Articles